School Renewal Investment Report
To provide a broader understanding of ongoing work that is taking place to renew and improve school facilities at TVDSB information is shared below regarding renewal projects that include:
- Renewal projects completed over the previous school year; and
- Renewal projects underway using existing School Condition Index and/or School Renewal Allocation funds.
| School Name | Project Description | Start Date | Completion Date or Anticipated Date for Completion | Percent Completed |
| B. Davison S.S. (Thames S.S.) | FIRE & LIFE SAFETY UPGRADES | 11/06/2023 | 12/15/2023 | 100 |
| Centennial Central P.S. | FIRE & LIFE SAFETY UPGRADES | 08/01/2024 | 08/31/2024 | 100 |
| Chippewa P.S. | FIRE & LIFE SAFETY UPGRADES | 02/05/2024 | 12/29/2023 | 100 |
| June Rose Callwood P.S. | FIRE & LIFE SAFETY UPGRADES | 06/27/2024 | 08/22/2024 | 100 |
| Lester B. Pearson School for the Arts | FIRE & LIFE SAFETY UPGRADES | 08/01/2024 | 03/31/2025 | 85 |
| Woodfield F.I. P.S. | FIRE & LIFE SAFETY UPGRADES | 06/28/2024 | 11/25/2024 | 100 |
| Old North P.S. | FIRE & LIFE SAFETY UPGRADES | 08/09/2023 | 11/08/2023 | 100 |
| Southside P.S. | FIRE & LIFE SAFETY UPGRADES | 08/01/2024 | 09/30/2024 | 100 |
| Trafalgar P.S. | FIRE & LIFE SAFETY UPGRADES | 08/01/2024 | 03/31/2025 | 85 |
| West Oaks F.I. P.S. | FIRE & LIFE SAFETY UPGRADES | 03/01/2024 | 09/30/2024 | 100 |
| East Elgin S.S. | FIRE & LIFE SAFETY UPGRADES | 08/01/2024 | 09/30/2024 | 100 |
| Glendale H.S. | FIRE & LIFE SAFETY UPGRADES | 06/24/2024 | 08/30/2024 | 99 |
| Huron Park S.S. | FIRE & LIFE SAFETY UPGRADES | 08/01/2024 | 08/31/2024 | 100 |
| Nicholas Wilson P.S. | ENHANCEMENTS | 07/02/2024 | 08/26/2024 | 100 |
| Eagle Heights P.S. | ENHANCEMENTS | 07/04/2023 | 01/01/2025 | 95 |
| West Elgin S.S. | ENHANCEMENTS | 06/28/2024 | 02/28/2025 | 70 |
| Westminster S.S. | ENHANCEMENTS | 12/18/2023 | 09/03/2024 | 98 |
| Byron Somerset P.S. | AODA COMPLIANCE | 03/11/2024 | 07/02/2024 | 100 |
| Cleardale P.S. | AODA COMPLIANCE | 11/16/2023 | 01/01/2024 | 100 |
| Glen Cairn P.S. | AODA COMPLIANCE | 07/02/2024 | 09/03/2024 | 100 |
| St. George’s P.S. | AODA COMPLIANCE | 07/02/2024 | 09/11/2024 | 100 |
| Huron Park S.S. | AODA COMPLIANCE | 06/03/2024 | 11/27/2024 | 98 |
| Montcalm S.S. | AODA COMPLIANCE | 04/02/2024 | 01/24/2025 | 80 |
| North Middlesex Dist. S.S. | AODA COMPLIANCE | 07/02/2024 | 08/30/2024 | 100 |
| London South C.I. | AODA COMPLIANCE | 07/02/2024 | 02/01/2024 | 100 |
| Blossom Pk Ed. Ctr., Woodstock | AODA COMPLIANCE | 10/01/2023 | 10/31/2023 | 100 |
| A.J. Baker P.S. | SPECIAL NEEDS ALTERATIONS | 08/01/2024 | 06/03/2024 | 100 |
| Arthur Ford P.S. | SPECIAL NEEDS ALTERATIONS | 09/18/2023 | 02/01/2024 | 100 |
| Central P.S., Woodstock | SPECIAL NEEDS ALTERATIONS | 02/06/2024 | 02/01/2024 | 100 |
| Dunwich-Dutton P.S. | SPECIAL NEEDS ALTERATIONS | 10/06/2023 | 02/01/2024 | 100 |
| Kensal Park P.S. | SPECIAL NEEDS ALTERATIONS | 11/15/2023 | 02/01/2024 | 100 |
| Orchard Park P.S. | SPECIAL NEEDS ALTERATIONS | 03/11/2024 | 02/01/2024 | 100 |
| Prince Charles P.S. | SPECIAL NEEDS ALTERATIONS | 10/09/2023 | 01/01/2024 | 100 |
| Princess Elizabeth P.S. (Ldn) | SPECIAL NEEDS ALTERATIONS | 11/15/2023 | 02/01/2024 | 100 |
| South Ridge P.S. | SPECIAL NEEDS ALTERATIONS | 10/04/2023 | 02/01/2024 | 100 |
| Straffordville P.S. | SPECIAL NEEDS ALTERATIONS | 10/02/2023 | 02/01/2024 | 100 |
| Tavistock P.S. | SPECIAL NEEDS ALTERATIONS | 03/11/2024 | 02/01/2024 | 100 |
| W. Sherwood Fox P.S. | SPECIAL NEEDS ALTERATIONS | 09/13/2023 | 01/01/2024 | 100 |
| Wilberforce P.S. | SPECIAL NEEDS ALTERATIONS | 10/16/2023 | 02/01/2024 | 100 |
| Laurie Hawkins P.S. | SPECIAL NEEDS ALTERATIONS | 08/13/2024 | 06/29/2024 | 100 |
| Mary Wright P.S. | SPECIAL NEEDS ALTERATIONS | 08/05/2024 | 06/28/2024 | 100 |
| College Avenue S.S. | SPECIAL NEEDS ALTERATIONS | 02/06/2024 | 02/01/2024 | 100 |
| East Elgin S.S. | SPECIAL NEEDS ALTERATIONS | 11/17/2023 | 02/01/2024 | 100 |
| Parkside Collegiate Institute | SPECIAL NEEDS ALTERATIONS | 11/06/2023 | 11/01/2023 | 100 |
| London South C.I. | SPECIAL NEEDS ALTERATIONS | 02/13/2024 | 03/01/2024 | 100 |
| B. Davison S.S. (Thames S.S.) | SPECIAL NEEDS ALTERATIONS | 01/02/2024 | 02/01/2024 | 100 |
| Southwold P.S. | PLUMBING SYSTEMS & SERVICES | 07/29/2024 | 08/31/2024 | 100 |
| Zorra Highland Park P.S. | PLUMBING SYSTEMS & SERVICES | 03/11/2024 | 08/29/2024 | 100 |
| North Middlesex Dist. S.S. | PLUMBING SYSTEMS & SERVICES | 07/05/2024 | 08/31/2024 | 100 |
| Ealing P.S. | PLUMBING SYSTEMS & SERVICES | 07/02/2024 | 12/16/2024 | 90 |
| East Williams Memorial P.S. | PLUMBING SYSTEMS & SERVICES | 07/02/2024 | 10/21/2024 | 100 |
| Elgin Court P.S. | WASHROOMS RENOVATION | 07/01/2024 | 11/08/2024 | 100 |
| Tecumseh P. S. | PLUMBING SYSTEMS & SERVICES | 06/01/2024 | 11/06/2024 | 100 |
| Oakridge S.S. | PLUMBING SYSTEMS & SERVICES | 10/20/2023 | 03/28/2024 | 100 |
| Ashley Oaks P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Bonaventure Meadows P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Central P.S., Woodstock | ROOF REPLACEMENT | 07/02/2024 | 08/23/2024 | 100 |
| Cleardale P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Davenport P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/27/2024 | 100 |
| Dunwich-Dutton P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| East Oxford Central P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/29/2024 | 100 |
| Eastdale P.S. | ROOF REPLACEMENT | 07/02/2024 | 07/25/2024 | 100 |
| Emily Carr P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/23/2024 | 100 |
| Forest City P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/30/2024 | 100 |
| Forest Park P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Glen Cairn P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/29/2024 | 100 |
| Hickson Central P.S. | ROOF REPLACEMENT | 07/02/2024 | 09/20/2024 | 100 |
| Jeanne Sauve F.I. P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/26/2024 | 100 |
| Woodfield F.I. P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Northridge P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Kettle Creek P.S. (Port Stanley) | ROOF REPLACEMENT | 07/03/2024 | 07/04/2024 | 100 |
| Riverside P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/20/2024 | 100 |
| J.S. Buchanan (Southdale P.S.) | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Southside P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Springfield P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/15/2024 | 100 |
| St. George’s P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Woodland Heights P.S. | ROOF REPLACEMENT | 07/02/2024 | 08/13/2024 | 100 |
| Zorra Highland Park P.S. | ROOF REPLACEMENT | 07/02/2024 | 09/25/2024 | 100 |
| Ingersoll District Collegiate Institute | ROOF REPLACEMENT | 07/02/2024 | 08/29/2024 | 100 |
| Montcalm S.S. | ROOF REPLACEMENT | 07/02/2024 | 08/23/2024 | 100 |
| North Middlesex Dist. S.S. | ROOF REPLACEMENT | 07/02/2024 | 08/29/2024 | 100 |
| Oakridge S.S. | ROOF REPLACEMENT | 07/02/2024 | 08/28/2024 | 100 |
| Strathroy District Collegiate Institute | ROOF REPLACEMENT | 07/02/2024 | 08/19/2024 | 100 |
| Lambeth P.S. | BOILER SYSTEM REPLACEMENT | 07/02/2024 | 12/02/2024 | 98 |
| Byron Northview P.S. | BOILER & HEATING SYSTEM REPLACEMENT | 06/03/2024 | 08/31/2024 | 100 |
| Byron Southwood P.S. | BOILER & HEATING SYSTEM REPLACEMENT | 06/03/2024 | 12/13/2024 | 100 |
| C.C.Carrothers P.S. | BOILER & HEATING SYSTEM REPLACEMENT | 10/27/2023 | 11/10/2023 | 100 |
| Woodstock Collegiate Institute | BOILER & HEATING SYSTEM REPLACEMENT | 07/01/2024 | 12/25/2024 | 98 |
| Sir Wilfrid Laurier S.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 07/01/2024 | 09/20/2024 | 90 |
| Glen Cairn P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 05/01/2024 | 01/20/2025 | 80 |
| Northdale P.S. (Woodstock) | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 07/02/2024 | 09/06/2024 | 100 |
| Oxbow P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 07/10/2023 | 12/22/2023 | 100 |
| Riverside P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 06/30/2023 | 08/29/2024 | 100 |
| Old North P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 05/20/2024 | 12/20/2024 | 95 |
| Sir John A. Macdonald P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) Phase 1 | 05/20/2024 | 08/29/2024 | 90 |
| Springfield P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 05/01/2023 | 02/13/2024 | 100 |
| Valleyview P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 07/08/2024 | 01/20/2025 | 70 |
| Arthur Voaden S.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 09/15/2024 | 09/30/2024 | 100 |
| College Avenue S.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 07/02/2024 | 08/29/2024 | 95 |
| Parkside Collegiate Institute | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) Phase 1 | 07/01/2024 | 08/29/2024 | 80 |
| Westminster S.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 07/02/2024 | 11/19/2024 | 100 |
| Jeanne Sauve F.I. P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 06/03/2024 | 08/31/2024 | 100 |
| Sir Georges Etienne Cartier P.S. | ELECTRICAL SERVICES & EQUIPMENT REPLACEMENT | 07/07/2024 | 08/29/2024 | 80 |
| Wortley Road P.S. | ELECTRICAL SERVICES & EQUIPMENT REPLACEMENT | 02/12/2024 | 09/13/2024 | 100 |
| Algonquin P.S. | FIRE ALARM REPLACEMENT | 06/01/2024 | 12/13/2024 | 88 |
| Ashley Oaks P.S. | FIRE ALARM REPLACEMENT | 10/22/2024 | 10/31/2024 | 99 |
| Woodland Heights P.S. | FIRE ALARM REPLACEMENT | 05/06/2024 | 12/13/2024 | 89 |
| Dunwich-Dutton P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 06/10/2024 | 07/08/2024 | 100 |
| John Wise P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 03/15/2024 | 05/17/2024 | 100 |
| Aberdeen P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| East Carling P.S. (Bishop Townshend) | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Bonaventure Meadows P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Chippewa P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Ealing P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Eastdale P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 05/06/2024 | 10/25/2024 | 98 |
| Evelyn Harrison P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Forest City P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Hillcrest P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Louise Arbour F.I. P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Jeanne Sauve F.I. P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| John P. Robarts P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Knollwood Park P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Lester B. Pearson School for the Arts | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Lord Nelson P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Lord Elgin P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Woodfield F.I. P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Northbrae P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Northridge P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Prince Charles P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Princess Anne FI P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Old North P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Sir John A. Macdonald P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| St. George’s P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Trafalgar P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Tweedsmuir P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Cedar Hollow P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Stoney Creek P.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Central S.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Clarke Road S.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/06/2023 | 10/18/2024 | 100 |
| H.B. Beal S.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| A.B. Lucas S.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Montcalm S.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| B. Davison S.S. (Thames S.S.) | INTERCOM & SECURITY SYSTEM REPLACEMENT | 11/13/2023 | 10/18/2024 | 100 |
| Arthur Voaden S.S. | WINDOW AND DOOR REPLACEMENT | 11/06/2023 | 01/31/2024 | 100 |
| H.B. Beal S.S. | WINDOW AND DOOR REPLACEMENT | 07/01/2024 | 08/31/2024 | 100 |
| Blossom Pk Ed. Ctr., Woodstock | WINDOW AND DOOR REPLACEMENT | 01/22/2024 | 02/29/2024 | 100 |
| Glencoe District H.S. | WINDOW AND DOOR REPLACEMENT | 07/02/2024 | 02/28/2025 | 70 |
| Centennial Central P.S. | WINDOW AND DOOR REPLACEMENT | 10/30/2023 | 01/31/2024 | 100 |
| Ealing P.S. | WINDOW AND DOOR REPLACEMENT | 07/02/2024 | 02/28/2025 | 80 |
| Ekcoe Central P.S. | WINDOW AND DOOR REPLACEMENT | 07/18/2023 | 05/31/2024 | 100 |
| Hickson Central P.S. | WINDOW AND DOOR REPLACEMENT | 01/15/2024 | 05/31/2024 | 100 |
| Riverside PS. | WINDOW AND DOOR REPLACEMENT | 10/23/2023 | 03/21/2024 | 100 |
| Springfield P.S. | WINDOW AND DOOR REPLACEMENT | 09/18/2023 | 11/30/2023 | 100 |
| Valleyview P.S. | WINDOW AND DOOR REPLACEMENT | 09/05/2023 | 01/31/2024 | 100 |
| College Avenue S.S. | WINDOW AND DOOR REPLACEMENT | 02/29/2024 | 03/29/2024 | 100 |
| Glencoe District H.S. | WINDOW AND DOOR REPLACEMENT | 03/11/2024 | 08/31/2024 | 100 |
| Glendale H.S. | WINDOW AND DOOR REPLACEMENT | 04/29/2024 | 08/31/2024 | 100 |
| North Middlesex Dist. S.S. | WINDOW AND DOOR REPLACEMENT | 09/05/2023 | 03/22/2024 | 100 |
| Woodstock Collegiate Institute | WINDOW AND DOOR REPLACEMENT | 05/27/2024 | 12/31/2024 | 97 |
| A.J. Baker P.S. | GROUNDS & ASPHALT REPAIR | 06/01/2024 | 07/31/2024 | 100 |
| Chippewa P.S. | GROUNDS & ASPHALT REPAIR | 12/01/2023 | 01/14/2024 | 100 |
| Davenport P.S. | GROUNDS & ASPHALT REPAIR | 09/06/2023 | 09/30/2023 | 100 |
| Harrisfield P.S. | GROUNDS & ASPHALT REPAIR | 07/02/2024 | 08/09/2024 | 100 |
| Roch Carrier F.I. P.S. | GROUNDS & ASPHALT REPAIR | 07/12/2024 | 08/30/2024 | 100 |
| Innerkip Central P.S. | GROUNDS & ASPHALT REPAIR | 07/02/2024 | 08/29/2024 | 100 |
| Knollwood Park P.S. | GROUNDS & ASPHALT REPAIR | 07/02/2024 | 08/29/2024 | 100 |
| Locke’s P.S. | GROUNDS & ASPHALT REPAIR | 09/06/2023 | 09/30/2023 | 100 |
| Lord Nelson P.S. | GROUNDS & ASPHALT REPAIR | 07/01/2024 | 08/31/2024 | 100 |
| McGillivray Central P.S. | GROUNDS & ASPHALT REPAIR | 10/15/2023 | 11/17/2023 | 100 |
| Prince Charles P.S. | GROUNDS & ASPHALT REPAIR | 07/19/2024 | 08/29/2024 | 100 |
| River Heights P.S. | GROUNDS & ASPHALT REPAIR | 10/15/2023 | 11/30/2023 | 100 |
| Southwold P.S. | GROUNDS & ASPHALT REPAIR | 08/12/2024 | 08/16/2024 | 100 |
| White Oaks P.S. | GROUNDS & ASPHALT REPAIR | 07/02/2024 | 08/28/2024 | 100 |
| Sir Arthur Currie P.S. | GROUNDS & ASPHALT REPAIR | 10/15/2023 | 11/15/2023 | 100 |
| Cedar Hollow P.S. | GROUNDS & ASPHALT REPAIR | 07/02/2024 | 08/29/2024 | 100 |
| Arthur Voaden S.S. | GROUNDS & ASPHALT REPAIR | 05/10/2024 | 08/31/2024 | 100 |
| Parkside Collegiate Institute | GROUNDS & ASPHALT REPAIR | 09/06/2023 | 09/30/2023 | 100 |
| Lambeth P.S. | GROUNDS & ASPHALT REPAIR | 01/19/2024 | 03/31/2024 | 100 |
| Dunwich-Dutton P.S. | GROUNDS & ASPHALT REPAIR | 11/27/2023 | 12/31/2023 | 100 |
| Lord Elgin P.S. | GROUNDS & ASPHALT REPAIR | 07/02/2024 | 08/29/2024 | 100 |
| Northbrae P.S. | GROUNDS & ASPHALT REPAIR | 07/02/2024 | 07/31/2024 | 100 |
| Saunders S.S. | GROUNDS & ASPHALT REPAIR | 07/20/2024 | 08/03/2024 | 100 |
| Davenport P.S. | MASONRY & CONCRETE RESTORATION | 07/02/2024 | 08/29/2024 | 100 |
| June Rose Callwood P.S. | MASONRY & CONCRETE RESTORATION | 08/26/2024 | 11/15/2024 | 100 |
| P. E. Trudeau F.I. P.S. | MASONRY & CONCRETE RESTORATION | 08/26/2024 | 11/15/2024 | 100 |
| Orchard Park P.S. | MASONRY & CONCRETE RESTORATION | 08/30/2024 | 08/31/2024 | 100 |
| South Dorchester P.S. | MASONRY & CONCRETE RESTORATION | 03/04/2024 | 03/21/2024 | 100 |
| Woodland Heights P.S. | MASONRY & CONCRETE RESTORATION | 08/01/2024 | 08/14/2024 | 100 |
| Central S.S. | MASONRY & CONCRETE RESTORATION | 07/02/2024 | 08/30/2024 | 98 |
| East Elgin S.S. | MASONRY & CONCRETE RESTORATION | 07/02/2024 | 07/31/2024 | 100 |
| Woodstock Collegiate Institute | MASONRY & CONCRETE RESTORATION | 08/19/2024 | 08/30/2024 | 100 |
| Annandale P.S. | MASONRY & CONCRETE RESTORATION | 07/08/2024 | 07/19/2024 | 100 |
| Bonaventure Meadows P.S. | MASONRY & CONCRETE RESTORATION | 05/27/2024 | 06/07/2024 | 100 |
| Delaware Central P.S. | MASONRY & CONCRETE RESTORATION | 07/02/2024 | 08/09/2024 | 100 |
| Masonville P.S. | MASONRY & CONCRETE RESTORATION | 03/25/2024 | 03/18/2024 | 95 |
| College Avenue S.S. | MASONRY & CONCRETE RESTORATION | 07/02/2024 | 08/30/2024 | 100 |
| A.J. Baker P.S. | ENERGY MANAGEMENT | 01/15/2024 | 05/16/2024 | 100 |
| Clara Brenton P.S. | ENERGY MANAGEMENT | 04/16/2024 | 04/01/2025 | 70 |
| Northdale Central P.S. | ENERGY MANAGEMENT | 10/01/2024 | 02/10/2024 | 60 |
| Northridge P.S. | ENERGY MANAGEMENT | 06/30/2024 | 04/01/2025 | 70 |
| Westmount P.S. | ENERGY MANAGEMENT | 06/30/2024 | 04/01/2025 | 70 |
| Wilfrid Jury P.S. | ENERGY MANAGEMENT | 05/06/2024 | 04/01/2025 | 60 |
| London South C.I. | ENERGY MANAGEMENT | 06/30/2024 | 04/01/2025 | 30 |
| Algonquin P.S. | INTERIOR FINISHES | 03/11/2024 | 03/25/2024 | 100 |
| Chippewa P.S. | INTERIOR FINISHES | 07/01/2024 | 08/31/2024 | 100 |
| Forest Park P.S. | INTERIOR FINISHES | 07/08/2024 | 07/31/2024 | 100 |
| P. E. Trudeau F.I. P.S. | INTERIOR FINISHES | 07/03/2024 | 08/31/2024 | 100 |
| Lester B. Pearson School for the Arts | INTERIOR FINISHES | 07/03/2024 | 07/31/2024 | 100 |
| Locke’s P.S. | INTERIOR FINISHES | 03/08/2024 | 04/18/2024 | 100 |
| McGregor P.S. | INTERIOR FINISHES | 07/15/2024 | 08/31/2024 | 100 |
| Northdale P.S. (Woodstock) | INTERIOR FINISHES | 07/02/2024 | 08/31/2024 | 100 |
| Plattsville & District P.S. | INTERIOR FINISHES | 07/02/2024 | 08/31/2024 | 100 |
| Springfield P.S. | INTERIOR FINISHES | 03/11/2024 | 03/15/2024 | 100 |
| University Heights P.S. | INTERIOR FINISHES | 12/01/2023 | 01/31/2024 | 100 |
| Victoria P.S. (London) | INTERIOR FINISHES | 07/01/2024 | 08/31/2024 | 100 |
| Westmount P.S. | INTERIOR FINISHES | 07/01/2024 | 07/31/2024 | 100 |
| Wortley Road P.S. | INTERIOR FINISHES | 07/01/2024 | 08/02/2024 | 100 |
| Annandale P.S. | INTERIOR FINISHES | 07/02/2024 | 08/31/2024 | 100 |
| Arthur Voaden S.S. | INTERIOR FINISHES | 07/03/2024 | 08/31/2024 | 100 |
| East Elgin S.S. | INTERIOR FINISHES | 03/11/2024 | 03/31/2024 | 100 |
| Glendale H.S. | INTERIOR FINISHES | 07/02/2024 | 07/25/2024 | 100 |
| A.B. Lucas S.S. | INTERIOR FINISHES | 07/03/2024 | 01/31/2025 | 90 |
| Westminster S.S. | INTERIOR FINISHES | 07/01/2024 | 08/31/2024 | 100 |
| Clarke Road S.S. | INTERIOR FINISHES | 07/01/2024 | 08/31/2024 | 100 |
| Knollwood Park P.S. | INTERIOR FINISHES | 07/02/2024 | 12/16/2024 | 97 |
| Mosa Central P.S. | INTERIOR FINISHES | 03/11/2024 | 11/01/2024 | 99 |
| Port Burwell P.S. | INTERIOR FINISHES | 11/29/2023 | 07/01/2024 | 100 |
| Central Elgin Collegiate Institute | CORRIDOR INFRASTRUCTURE | 07/02/2024 | 11/01/2024 | 99 |
| Clarke Road S.S. | CORRIDOR INFRASTRUCTURE | 07/02/2024 | 01/13/2025 | 80 |
| Montcalm S.S. | INTERIOR FINISHES | 06/01/2024 | 12/15/2024 | 75 |
| Algonquin P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 08/14/2024 | 100 |
| Ashley Oaks P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 07/31/2024 | 100 |
| Central P.S., Woodstock | SCHOOL PROGRAM IMPROVEMENT | 04/01/2024 | 08/31/2024 | 100 |
| Chippewa P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 07/31/2024 | 100 |
| East Elgin S.S. | SCHOOL PROGRAM IMPROVEMENT | 10/09/2024 | 10/18/2024 | 100 |
| East Oxford Central P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 08/31/2024 | 98 |
| Eastdale P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 08/31/2024 | 100 |
| Ekcoe Central P.S. | SCHOOL PROGRAM IMPROVEMENT | 06/17/2024 | 08/31/2024 | 100 |
| Evelyn Harrison P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 03/14/2025 | 0 |
| Roch Carrier F.I. P.S. | SCHOOL PROGRAM IMPROVEMENT | 01/08/2024 | 01/31/2024 | 100 |
| Knollwood Park P.S. | SCHOOL PROGRAM IMPROVEMENT | 08/26/2024 | 08/30/2024 | 100 |
| Lord Nelson P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 09/10/2024 | 100 |
| McGillivray Central P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 07/31/2024 | 100 |
| Port Burwell P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 09/13/2024 | 100 |
| Sir John A. Macdonald P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 08/31/2024 | 100 |
| Southwold P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/08/2024 | 08/31/2024 | 100 |
| Wilton Grove P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/01/2024 | 07/31/2024 | 100 |
| Mitchell Hepburn P.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 07/01/2024 | 100 |
| Sir Frederick Banting S.S. | SCHOOL PROGRAM IMPROVEMENT | 05/01/2024 | 04/30/2024 | 100 |
| Central Elgin Collegiate Institute | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 08/31/2024 | 100 |
| Sir Wilfrid Laurier S.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 08/31/2024 | 100 |
| Montcalm S.S. | SCHOOL PROGRAM IMPROVEMENT | 07/02/2024 | 07/31/2024 | 100 |
| Oakridge S.S. | SCHOOL PROGRAM IMPROVEMENT | 03/18/2024 | 08/29/2024 | 90 |
| Parkside Collegiate Institute | SCHOOL PROGRAM IMPROVEMENT | 06/15/2023 | 09/15/2023 | 100 |
| Ingersoll District Collegiate Institute | FIRE & LIFE SAFETY UPGRADES | 09/16/2024 | 08/31/2025 | 25 |
| Saunders S.S. | FIRE & LIFE SAFETY UPGRADES | 11/01/2024 | 08/31/2025 | 0 |
| Algonquin P.S. | SPECIAL NEEDS ALTERATIONS | 09/16/2024 | 08/31/2025 | 98 |
| Lord Nelson P.S. | SPECIAL NEEDS ALTERATIONS | 10/11/2024 | 08/31/2025 | 95 |
| Tecumseh P.S. | SPECIAL NEEDS ALTERATIONS | 11/15/2024 | 08/31/2025 | 40 |
| Westmount P.S. | SPECIAL NEEDS ALTERATIONS | 11/13/2024 | 08/31/2025 | 90 |
| Lord Dorchester S.S. | SPECIAL NEEDS ALTERATIONS | 11/15/2024 | 08/31/2025 | 90 |
| Medway H.S. | SPECIAL NEEDS ALTERATIONS | 10/21/2024 | 08/31/2025 | 10 |
| Centennial Central P.S. | ROOF REPLACEMENT | 11/15/2024 | 08/31/2025 | 15 |
| Arthur Ford P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 12/02/2024 | 08/31/2025 | 5 |
| P.E. Trudeau F.I. P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 10/21/2024 | 08/31/2025 | 10 |
| Port Burwell P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) | 12/02/2024 | 08/31/2025 | 10 |
| Sir John A. Macdonald P.S. | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) Phase 2 | 12/01/2024 | 08/31/2025 | 10 |
| Parkside Collegiate Institute | HEATING, VENTILATION & AIR CONDITIONING SYSTEMS (HVAC) Phase 2 | 01/02/2025 | 08/29/2025 | 2 |
| Westmount P.S. | ELECTRICAL SERVICES & EQUIPMENT REPLACEMENT | 06/02/2025 | 08/31/2025 | 0 |
| A.B. Lucas S.S. | ELECTRICAL SERVICES & EQUIPMENT REPLACEMENT | 07/02/2025 | 08/31/2025 | 0 |
| Glendale H.S. | INTERCOM & SECURITY SYSTEM REPLACEMENT | 09/24/2024 | 08/31/2025 | 20 |
| Central P.S., Woodstock | MASONRY & CONCRETE RESTORATION | 03/01/2025 | 08/31/2025 | 5 |
| Central P.S., Woodstock | FIRE & LIFE SAFETY UPGRADES | 09/23/2024 | 08/31/2025 | 85 |
| Saunders S.S. | ENERGY MANAGEMENT | 01/02/2025 | 08/31/2025 | 0 |
| Strathroy District Collegiate Institute | ENERGY MANAGEMENT | 12/05/2024 | 08/31/2025 | 0 |
| Prince Charles P.S. | INTERIOR FINISHES | 08/22/2024 | 08/31/2025 | 30 |
| Bonaventure Meadows P.S. | SCHOOL PROGRAM IMPROVEMENT | 10/28/2024 | 10/31/2024 | 100 |